2601Mallard Ridge Subdivision — Storm Drainage
Example Homes of the Carolinas · Mallard Ridge Dr, Charlotte · Aug 27, 2026 to Jan 29, 2027
Active
Summary
Where the job stands, who's on it, and the way into everything else.
Money in
From the customer
- Contractwith $8,450 of signed changes
- $1,046,200
- Changes not signed yet
- $23,900
- Billed
- $486,300
- Received
- $412,900
- Owed to us$48,630 of it retainage
- $73,400
Money out
To vendors and subs
- CommittedPurchase orders and subcontracts
- $312,400
- Billed to us
- $168,250
- Paid
- $141,900
- Still to be billedOn open commitments
- $144,150
Team
- Project manager
- Wade Hollis
- Superintendent
- Marcus Hill
- Complete
- 47%