2601Mallard Ridge Subdivision — Storm Drainage

Example Homes of the Carolinas · Mallard Ridge Dr, Charlotte · Aug 27, 2026 to Jan 29, 2027

Active

Summary

Where the job stands, who's on it, and the way into everything else.

Money in

From the customer

Contractwith $8,450 of signed changes
$1,046,200
Changes not signed yet
$23,900
Billed
$486,300
Received
$412,900
Owed to us$48,630 of it retainage
$73,400

Money out

To vendors and subs

CommittedPurchase orders and subcontracts
$312,400
Billed to us
$168,250
Paid
$141,900
Still to be billedOn open commitments
$144,150

Team

Project manager
Wade Hollis
Superintendent
Marcus Hill
Complete
47%