Arrowood Commerce Center Pad
Example Development Partners · Arrowood Rd, Charlotte · bid day Oct 3, 2026
| Description | Quantity | Unit | Total | ||
|---|---|---|---|---|---|
| Site preparation | |||||
| Mobilization | 1 | LS | $38,500 | ||
| Clearing and grubbing | 14.2 | AC | $68,870 | ||
| Silt fence, installed and maintained | 6,420 | LF | $21,828 | ||
| Construction entrance | 2 | EA | $7,800 | ||
| Earthwork | |||||
| Unclassified excavation | 48,300 | CY | $234,255 | ||
| Borrow excavation, placed and compacted | 11,650 | CY | $111,840 | ||
| Fine grading, building pads and lots | 38,900 | SY | $36,955 | ||
| Storm drainage | |||||
| 15" RCP, Class III | 1,840 | LF | $114,080 | ||
| 18" RCP, Class III | 1,265 | LF | $93,610 | ||
How the unit price is built Labor $20.72Equipment $17.76Material $35.52 | |||||
| 24" RCP, Class III | 690 | LF | $66,240 | ||
| Curb inlet, NCDOT 840.02 | 22 | EA | $102,300 | ||
| Junction box, 4' x 4' | 6 | EA | $32,400 | ||
| Water and sewer | |||||
| 8" DIP water line | 3,120 | LF | $180,960 | ||
| Fire hydrant assembly | 9 | EA | $61,650 | ||
| 8" PVC sanitary sewer, 6–10' deep | 2,760 | LF | $176,640 | ||
| 4' sanitary manhole | 14 | EA | $72,800 | ||
| Paving | |||||
| ABC stone base, 8" | 15,400 | SY | $218,680 | ||
| Asphalt S9.5B surface, 2" | 1,710 | TON | $191,520 | ||
| Curb and gutter, 2'-6" | 6,980 | LF | $150,070 | ||