Riverbend Subdivision, Phase 1

Example Homes of the Carolinas · Bond estimate

DescriptionQuantityUnitTotal
Mobilization1LS$98,000
Unclassified excavation8,400CY$155,400
Geotextile for soil stabilization3,600SY$11,160
Aggregate base course2,950TON$135,700
Asphalt concrete surface course, S9.5B1,240TON$146,320
15" RC pipe culverts, Class III860LF$67,080
24" RC pipe culverts, Class III410LF$45,920
Drop inlet, NCDOT 840.1414EA$68,600
Concrete sidewalk, 5"2,380SY$147,560
Seeding and mulching4.6ACR$15,640
Work zone signs (stationary)420SF$3,990
Subtotal$895,370
Contingency 10%$89,537
Opinion of probable construction cost$984,907